搜索答案

单选题 The operation of the steam purge line, stated incorrectly is ( ).

A、 The pipeline memory water should be fully removed before opening the sweeping steam
B、 the steam pipe with a trap should be opened and cut water
C、 such as water hammer phenomenon, should turn down or close the purging steam, strengthen the dehydration and heating pipe and then gradually open
D、 before purging the pipeline to ensure smooth, no need to dehydrate

微信扫一扫
扫一扫下载APP
微信小程序答题 下载APP答题
由4l***ds提供 分享 举报 纠错

相关试题

单选题 A gas explosiometer measures the ( ) of combustible gases.

A、 lower explosive limit
B、 Upper explosive limit
C、 explosion limit range
D、 mass concentration

单选题 When the chemical equipment is hot repair, the medium that can not be directly used to replace the combustible gas is ( ).

A、 helium
B、 Nitrogen
C、 Argon
D、 Air

单选题 When the height of the high work is ( ) m, it is called the level 2 high work.

A、 2 ~ 10
B、 5 to 10
C、 5 to 15
D、 10 to 15

单选题 High work means work performed above the fall height datum ( ) (inclusive), where there is a possibility of falling.

A、 2 m
B、 2.5m
C、 3 m
D、 5 m

单选题 For ( ) (including) above high work, the "high work permit" should be applied.

A、 10 m
B、 15 m
C、 20 m
D、 30 m

单选题 ( ) Does not fall under fall protection.

A、 Safety belt
B、 Safety net
C、 hard hat
D、 Safety rope

单选题 When doing hot fire analysis, the interval between sampling and hot fire is more than ( ) minutes, or the stop time in the middle of hot work is more than ( ) minutes, you must resamb for analysis.

A、 30,30
B、 30,60
C、 60,30
D、 60,60

单选题 For hot operation in the no-fire zone, the distance between the oxygen cylinder and the acetylene cylinder is at least ( ) meters.

A、 2
B、 3
C、 4