Before starting the steam ejector to vacuum, the following operation error is ( ).
The tower does not condense too much, the vacuum system load ( ).
A complete vacuuming system generally consists of ( ).
The medium used for vacuuming the decompression tower before construction is ( ).
When the steam opening process is used for vacuuming, make sure ( ).
When vacuuming before startup, should ( ).
When vacuuming test before startup, the speed of vacuuming should not be too fast, otherwise it will ( ).
Before starting the steam injector to vacuum, the following operations are correct ( ).
The furnace must be done ( ) before ignition of the heating furnace.
Before firing the furnace, ( ) need not be changed into the appropriate medium.
When the furnace starts ignition, the following flue baffle adjustment operation is correct ( ).
Before firing the heater, you must make sure ( ).
What is wrong with the following statement about furnace purging before commencement is ( ).
Standard for furnace purge before ignition: combustible gas content less than ( ).
The following furnace purge operation is wrong by ( ).